Working with Gantt Chart with RTC 3.0.1.2
I need following information related to Gantt Chart while working in RTC 3.0.1.2.
1.Which attributes or fields are required (optional/mandatory) for creating Gantt Chart
2.Are there any APIs realted to Gantt chart which I can use to do customization using plugin development
3.Can we produce Gantt Chart using custom fields (or attributes) instead of which are provided in RTC 3.0.1.2,
4.Is there any central information area where I can know more about RTC Gantt Charts
5.Complete process with internal details on how RTC produces Gantt Charts.
2 answers
For example https://jazz.net/library/article/590 talks about it in general and also shows how formal planning works in general. I think most of https://jazz.net/library/article/657 also applies to RTC 3.x.
1.Which attributes or fields are required (optional/mandatory) for creating Gantt Chart
2.Are there any APIs realted to Gantt chart which I can use to do customization using plugin development
3.Can we produce Gantt Chart using custom fields (or attributes) instead of which are provided in RTC 3.0.1.2,
4.Is there any central information area where I can know more about RTC Gantt Charts
5.Complete process with internal details on how RTC produces Gantt Charts.
1. You need an estimate for the work and a resource assigned
2. As far as I am aware, there is no official API for extending the planning component
3. No, actually the scheduling information is stored in the plan snapshots and not in the work item.
4. There is some information in the help. The Library is an additional resource.
5. This exceeds the scope of this forum.
Comments
Subrit Dikshit
Aug 19 '12, 10:15 a.m.Is jazz team really looking at forum sections, I really am not sure about it. If yes, please reply.