pre-populating RTC project plan as part of initial project setup
Is it possible to populate the plan created by WI's either from a WI template or otherwise as part of the initial project setup? |
One answer
Ralph Schoon (63.5k●3●36●46)
| answered Jan 21 '13, 1:35 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Bhwana, to have a plan show a work item you basically have to assign it to a category and set an iteration. I am not sure if you can do that in the project setup. You could look into the process configuration if you can assign values there.
|
Your answer