Jazz Forum Welcome to the Jazz Community Forum Connect and collaborate with IBM Engineering experts and users

how is critical path calculated in the plan

 My understanding of "Critical path" is that the "Earliest start date" of all WIs assigned to the iteration are equal to "Latest start date" and also "Earliest finish date" are equal to "Latest finish date" according to the online Help However it seems not working that way.  Please see the attached screenshots.
   <Quotes from IC >
   ----------------   
   If the slack is zero, the task or activity is critical and is highlighted in the Gantt chart view. On the critical path, none of the activities have slack, that is, for all
 these activities, ES=LS and EF=LF. A delay in an activity on the critical path delays the project.

In the image below there are no constraints still all 3 tasks are marked as critical when there are 30 days left in the Iteration. Critical path

0 votes



One answer

Permanent link
By default the work item constraint is As Soon As Possible. This means the task should be scheduled as soon as there is a free time.
This is the reason why there is no slack for the task. This is the reason why the tasks were marked as critical.
If we had supported the As Late As Possible constraint then we would have taken the iteration end date and had scheduled from reverse, even then the work items would had been critical.
One of the best way is to control the planned dates is by using the constraint dates.

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,025
× 239

Question asked: Oct 16 '12, 2:03 a.m.

Question was seen: 5,341 times

Last updated: Oct 16 '12, 2:04 a.m.

Confirmation Cancel Confirm