I am executing a RPT(Rational Performace Tester) schedule  containing multiple stages from RQM.
In the RPT workbench ,if we right click on the result and select 'Compare All time ranges' the data corresponding to each stage is displayed seperately.However,the default performance report that is sent to the RQM server doesnot contain the information for each schedule stage separately.
Is there any setting by which I can see the data for each stage of the schedule in the RQM?

One answer



permanent link
Ara Masrof (3.2k15) | answered Dec 30 '14, 10:54 a.m.
JAZZ DEVELOPER
The RPT result within RQM (an HTML file) will include that standard RPT information (Summary, Page Performance, Response vs Time Summary....etc), however there is no added functionality to compare Time Ranges; this would have to be done within the RPT UI (essentially you have no Right-Click functionality in the HTML report as you do in the RPT UI)