Hi All


1)  Is it possible to access the editor presentations of Test Plan, Test Case and Test Script, modify the same.                                    

For Example:  Remove the summary and formal review sections of test script or remove the weight and  
                        estimate of a test case in the summary section.                                                      
                                  
                                                                          
2. Is it possible to implement some rules in the process of RQM work flow w.r.t Test plan or a Test Case?                                    

 For Example:  To make the originator, the owner of the test  case/plan/script when created.

                                                                 or

The test case cannot be sent to review until the state has been set to ready for review similarly for approval.     


NOTE:     I have tried to check editor presentation options in RQM Project area management and also accessing through RTC eclipse client. However was not able to get to modifying these.

Any idea on how this can be achieved ?


Thanks in advance

Regards
Rajesh

One answer



permanent link
Pramod Chandoria (2.1k11220) | answered Jul 24 '12, 9:17 a.m.
JAZZ DEVELOPER
Hi Rajesh,
You can configure the sections for Test Case, Test Plan, Test Suite using manage section or customize the template when resource is created. However certain fields can not be removed like weight, estimate which appears on summary page.

You can use process advisers to configure what is prerequisite before an operation is executed. In 4.0 following advisers are available:
E-signature Required for Lock/Unlock
E-signature Required for Test Case Formal Review
E-signature Required for Execution Result Formal Review
Disallow Saving of Test Suites with State Approved or Retired
Disallow Transition to Approved until All Approvers Approve
Disallow Transition to Approved until All Reviewers/Approvers Approve
Disallow Transition to Approved until Required Approvers Approve
Disallow Transition to Approved until All Test Cases Approved
Disallow Transition to Reviewed until All Reviewers Approve
Disallow Transition to Reviewed until Required Reviewers Approve
Disallow Transition to Under Review until Approvers Defined
Disallow Transition to Under Review until Associated Work Items Resolved
Disallow Transition to Under Review until Reviewers Defined

You really need RTC  client to configure this process.
See Process application and customization section in http://www.ibm.com/developerworks/rational/library/rational-quality-manager-4.0/index.html