"Small one-off projects" configuration
All,
We have a couple of groups that are going to be doing a couple of 1-3month projects with different deadlines. They all have an Overall Theme, but I don't want to create 20+ RTC/RQM projects. So I am thinking one project, and multiple teams/categories. My main issue is project A might be due April 15th, project C&D might be due on April 20th, project E on April 30th. Does this mean different timelines, or am I missing an easier solution to implement this? The main thing with this is that it's almost Team Lead led, not management. So access is small, and they just want status, not anything major... |
One answer
Geoffrey Clemm (30.1k●3●30●35)
| answered Mar 23 '16, 2:40 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
From an RTC perspective, I would definitely do these in one project area, with separate timelines for when the schedules do not line up. I'll defer to the RQM experts on the RQM setup.
|
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.