RTC 3.0 planned start and end date
8 answers
Hi Sandra.
Plan dates are populated from Snapshots of type "Plan" (similarly, Proposed Dates are populated from Snapshots of type "Proposed").
To populate these dates, please create a Planned Snapshot (in the Snapshots tab). A Planned Snapshot will take a snapshot of the current plan. At that point (once a Plan Snapshot exists) the Start and End Dates in the snapshot will populate the Plan Start and Plan End dates in the plan itself. There can only be one Plan Snapshot
We understand this is not obvious and we are working on ways to make this more clear.
Thanks,
- Lucinio Santos
Plan dates are populated from Snapshots of type "Plan" (similarly, Proposed Dates are populated from Snapshots of type "Proposed").
To populate these dates, please create a Planned Snapshot (in the Snapshots tab). A Planned Snapshot will take a snapshot of the current plan. At that point (once a Plan Snapshot exists) the Start and End Dates in the snapshot will populate the Plan Start and Plan End dates in the plan itself. There can only be one Plan Snapshot
We understand this is not obvious and we are working on ways to make this more clear.
Thanks,
- Lucinio Santos
Sandra,
One more clarification point. The previous post (about creating a Snapshot of type "Plan" to populate the Planned Start and End dates) refers to the Plan editor (you will see a "Snapshot" tab in the plan editor where you can crate a snapshot of type "plan").
You may have seen those Planned Start and End dates as attributes in a work item. The above still applies. The Planned Start and End dates seen in a work item are the same dates seen in the "Work Breakdown and Schedule" view of in the plan editor. Once you create a snapshot of type "plan" you will see the Planned Start and End dates populated in the work item view.
- Lucinio Santos
One more clarification point. The previous post (about creating a Snapshot of type "Plan" to populate the Planned Start and End dates) refers to the Plan editor (you will see a "Snapshot" tab in the plan editor where you can crate a snapshot of type "plan").
You may have seen those Planned Start and End dates as attributes in a work item. The above still applies. The Planned Start and End dates seen in a work item are the same dates seen in the "Work Breakdown and Schedule" view of in the plan editor. Once you create a snapshot of type "plan" you will see the Planned Start and End dates populated in the work item view.
- Lucinio Santos
Hello as I understand correctly, is the scheduling only working correctly in the Formal Planning Template?
I have a project migrated from 2.0 based on the OpenUP template. There the Gantt Chart ("Roadmap") works but I cannot change the work item start dates (as on snapshot tab available).
The main problem is that the Gantt Chart shows a really incorrect order of the workitems in the timeline and there is no way to influence it.
For example a developer has two tasks A and B. B depends on A, but in the Roadmap B is scheduled earlier then A. As B depends on A it is impossible to perform task B before task A.
If there is a way to influence the order, please let me know.
I have a project migrated from 2.0 based on the OpenUP template. There the Gantt Chart ("Roadmap") works but I cannot change the work item start dates (as on snapshot tab available).
The main problem is that the Gantt Chart shows a really incorrect order of the workitems in the timeline and there is no way to influence it.
For example a developer has two tasks A and B. B depends on A, but in the Roadmap B is scheduled earlier then A. As B depends on A it is impossible to perform task B before task A.
If there is a way to influence the order, please let me know.
Hi,
see my enhancement request here
http://jazz.net/jazz/web/projects/Rational%20Team%20Concert#action=com.ibm.team.workitem.viewWorkItem&id=150159
see my enhancement request here
http://jazz.net/jazz/web/projects/Rational%20Team%20Concert#action=com.ibm.team.workitem.viewWorkItem&id=150159
Hello as I understand correctly, is the scheduling only working correctly in the Formal Planning Template?
I have a project migrated from 2.0 based on the OpenUP template. There the Gantt Chart ("Roadmap") works but I cannot change the work item start dates (as on snapshot tab available).
The main problem is that the Gantt Chart shows a really incorrect order of the workitems in the timeline and there is no way to influence it.
For example a developer has two tasks A and B. B depends on A, but in the Roadmap B is scheduled earlier then A. As B depends on A it is impossible to perform task B before task A.
If there is a way to influence the order, please let me know.
I believe the key here is that most software dependencies are not
start/end, but rather end/end ... i.e. when a software task A depends on
another software task B, then there is almost always some work you can
perform on software task A before software task B is started ... but you
cannot *complete* task A until task B is completed.
I've submitted work item 150827, requesting that end/end dependencies be
supported, and that in particular, the existing depends-on/blocks
relation be given end/end semantics (since many people are confused when
the depends-on/blocks relation does not result in a schedule dependency).
Cheers,
Geoff
On 1/18/2011 10:23 AM, schinal wrote:
start/end, but rather end/end ... i.e. when a software task A depends on
another software task B, then there is almost always some work you can
perform on software task A before software task B is started ... but you
cannot *complete* task A until task B is completed.
I've submitted work item 150827, requesting that end/end dependencies be
supported, and that in particular, the existing depends-on/blocks
relation be given end/end semantics (since many people are confused when
the depends-on/blocks relation does not result in a schedule dependency).
Cheers,
Geoff
On 1/18/2011 10:23 AM, schinal wrote:
Hi,
see my enhancement request here
http://jazz.net/jazz/web/projects/Rational%20Team%20Concert#action=com.ibm.team.workitem.viewWorkItem&id=150159
schinalwrote:
Hello as I understand correctly, is the scheduling only working
correctly in the Formal Planning Template?
I have a project migrated from 2.0 based on the OpenUP template.
There the Gantt Chart ("Roadmap") works but I cannot change
the work item start dates (as on snapshot tab available).
The main problem is that the Gantt Chart shows a really incorrect
order of the workitems in the timeline and there is no way to
influence it.
For example a developer has two tasks A and B. B depends on A, but
in the Roadmap B is scheduled earlier then A. As B depends on A it is
impossible to perform task B before task A.
If there is a way to influence the order, please let me know.
That I could not achieve. I see planned dates on a Plan but at the work item editor view it does not sync. I've already checked that the WI is planned for the same interation of the plan I took the snapshot. Its a bug of 3.0?
best regards
Condack
best regards
Condack
Sandra,
One more clarification point. The previous post (about creating a Snapshot of type "Plan" to populate the Planned Start and End dates) refers to the Plan editor (you will see a "Snapshot" tab in the plan editor where you can crate a snapshot of type "plan").
You may have seen those Planned Start and End dates as attributes in a work item. The above still applies. The Planned Start and End dates seen in a work item are the same dates seen in the "Work Breakdown and Schedule" view of in the plan editor. Once you create a snapshot of type "plan" you will see the Planned Start and End dates populated in the work item view.
- Lucinio Santos