JRS report builder - show Planned Work & Actual Work in hours?
I found this post: https://jazz.net/forum/questions/207656/jrsreport-builder-are-the-estimate-or-time-spent-attributes-reportable
And I was wondering if there is any way in Report Builder to show the Planned Work & Actual Work values in hours instead of in seconds?
I want to use the reports as widgets in dashboards, so while I could personally live with an Excel export as well, our userbase wouldn't consider that an acceptable trade-off :-)
|
Accepted answer
Yes, you can exprss values in hours instead of in seconds.
Check out https://jazz.net/pub/new-noteworthy/jrs/6.0.4/6.0.4/6.0.4/index.html and search for Show in hours a value that is expressed in seconds in the data warehouse. NOTE that you need JRS 6.0.4.
Vicky Pagnaer selected this answer as the correct answer
|
One other answer
One caveat that isn't obvious in the New & Noteworthy is that if you have "Allow only report managers to edit queries" turned on for your data source, you must have Report Manager permissions in Report Builder in order to use the Custom Expression features.
|
Your answer