Jazz Forum Welcome to the Jazz Community Forum Connect and collaborate with IBM Engineering experts and users

Report Builder: Inconsistent Data - Planned Work vs Actual Work

 Good day,


We have picked up a couple of issues with regards to Report Builder 6.0.4, and how the time values (Planned Work, and Actual Work) are returned when a query/report is run.

In the scenario, we would like to compare the amount of time estimated for tasks, against the actual time taken.

Issue 1: Conversion of Planned Work, and Actual Work to Hours: Using the Custom Expression option, an attempt to convert the time allocated (Estimated/Actual) from seconds to hours using ($Tasks:Actual Work$/(60*60)) or $Tasks:Actual Work$/3600. If the value estimated is for 1800 (the expected value is 0.5), Report Builder returns 0 (or 0.00 if you show the result as decimal). 

Issue 2: Estimation on the task does not show the same values as report. For Example, the task has the following attributes filled in as follows:
- Estimate : 5 hours
- Correction: 4 hours
- Time remaining: 4 hours
The report when run in Report Builder shows the following values:
- Planned Work : 14,400 (in seconds) or 4 hours
- Actual Work: 0 
Could someone please guide me on the mappings of Estimation, and Correction in a task, to the attributes used in the actual report? and why is the report showing 4 hours in the report, instead of 5 hours?

Issue 3: Drill Downs of Reports: So, after the report has been generated, a Grouped Bar Graph is used to present the data that is returned, showing a bar with Estimates, and a bar with "Actuals". Both bars show that there are values that have been returned, but when drilling into the bar with "actuals", the table shows 0s (zeros), and when all "Actual" values are added from the table for example, the sum does not give the same result as that shown in the graph.

We have recreated these reports multiple times, and we seem to get the same inconsistencies across the various project areas reported against.

Could this be a known issue, a bug, or something we are missing?

Thank you.

Alick

1 vote



One answer

Permanent link
Issue 2: Estimation on the task does not show the same values as report. For Example, the task has the following attributes filled in as follows:
- Estimate : 5 hours
- Correction: 4 hours
- Time remaining: 4 hours

The estimated value is in "Estimate" or in "Correction" if the latter has been set. The Correction overwrites the Estimate and the old estimate value is documentation only, as it can not be changed if a correction has been set.

So the estimated work is 4 hours and since there are still 4 hours remaining, no work has been done and the calculation is correct.

0 votes

Comments

 Hi Ralph,


Thank you for your response.

We have a use case to compare, or rather evaluate our team's estimation accuracy using the data entered in the Jazz solution. Could you please guide on:
1. Reporting on the value of the Estimation 
2. Reporting on the actual time spent.

Thank you.

Alick

1 vote

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,019
× 7,495

Question asked: Jun 06 '18, 11:02 a.m.

Question was seen: 2,851 times

Last updated: Jun 07 '18, 9:04 a.m.

Confirmation Cancel Confirm