Two simple JRS Defect reports
CLM 603
|
One answer
For the "1. Defect burndown for a plan" report, you can use the existing "Burndown by work item count" ready-to-use report with some filters selected.
For the "2. Stacked bar weekly of status of defects for a plan" report, under "Focus on Artifact Trends" select "Work Item > Totals"; Under Condition, add Type and Planned For; Under Format select "Total Work Items" for the "Y axis".
|
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.