How are burnUp reports calculated? Based on which time?

Users asked following questions for burnUp report but I could not find details for burnUp report

Information I found for the BurnUP report are:
https://jazz.net/help-dev/clm/index.jsp?topic=%2Fcom.ibm.jazz.reports.doc%2Ftopics%2Fr_report_templates_oob.html
https://jazz.net/wiki/bin/view/Main/StatusJuly2709

Basically they want to know how each graphs are calculated. and what is based on?

Q1. Completed work
Are Hours of completed work based on Estimated or Time Spent or Corrected time?
How are Hours of completed work calculated?

Q2. Planned work.
How are Hours of Planned work calculated? based on which time (Estimated, Time Spend, Corrected time)?

Q3. Expected complete
How is this calculated?

Q4. Linear complete
How is this calculated?

Q5. Total Capacity
How is this calculated?
And what would happen if new members are added in the team?

Q6 Capacity BurnUP
How is this calculated?
And what would happen if new members are added in the team?

Thank you!

0 votes


Accepted answer

Permanent link
Q1. Completed work 
Are Hours of completed work based on Estimated or Time Spent or Corrected time? 
> If Corrected time specified, Corrected time otherwise Estimated. See below for the formula. 
How are Hours of completed work calculated? 
> For a particular timestamp, Corrected time or Estimated(for those CLOSED work items)  +  Time Spent (for those OPEN work items)

Q2. Planned work. 
How are Hours of Planned work calculated? based on which time (Estimated, Time Spend, Corrected time)? 
> If Corrected time specified, Corrected time otherwise Estimated

Q3. Expected complete 
How is this calculated? 
>Assume you were at day 2 of your 14 days iteration, Total Planned work * ( 2/14)

Q4. Linear complete 
How is this calculated? 
>Assume the first date of your iteration is 9/7 and the last date is 9/20. Thus, the middle date is 9/14.  And you were at day 2 of your iteration, Total Planned work on 9/14 * ( 2/7) 

Q5. Total Capacity 
How is this calculated? 
And what would happen if new members are added in the team? 
> Pls refer to the Team_Capacity table on this link. https://jazz.net/wiki/bin/view/Main/DataWarehouseSnapshotSchemas20 

Q6 Capacity BurnUP 
How is this calculated? 
And what would happen if new members are added in the team?
> Pls refer to the Team_Capacity table on this link. https://jazz.net/wiki/bin/view/Main/DataWarehouseSnapshotSchemas20 
ryosuke oka selected this answer as the correct answer

2 votes

Comments

Thank you for your detailed answer, Clement!

this will help my customer as well as other customer who is looking for this kind of information.

Hi Clement, I had checked URL for Capacity and need to confirm about Question for Q5. since the capacity is calculated by date & Team, in theory The capacity goes up If we add a new member, right?

Do you think my understanding for the capacity is correct?

Thank you.

Yes, you're right.


One other answer

Permanent link
And you can also import the out-of-box burnup template into your BIRT development environment and the key dataset you should look into that contains the calculation logic is the "Burnup". 

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,019
× 7,495
× 239
× 230

Question asked: Sep 12 '12, 9:50 p.m.

Question was seen: 6,804 times

Last updated: Sep 19 '12, 11:06 a.m.

Confirmation Cancel Confirm