I may have missed it, but is there a widget or report that ties Work items and Test for a given iteration?
Example
Are all of the work items for this sprint covered by test cases?
I know there is the traceability view, but since there seems to be a ton of requirements/tests Shared reports and widgets, I was wondering if this is available for Work Items.
3 answers
Hello Sterling, There doesnt seem to be any out of the box report which can give such a data and hence feed the widget using it..
Have you tried report customization with RRDI / Insight? Once you create such a report you should be able to create a widget which feeds from the report.
Best Regards, Sunil
On second thought, you can create your own query in the Change Management application. Use the Planned For value to select work items by iteration and then add the Related Test Case column to the results display. Something like this:
Would that give you the information you need?
If you want to identify work items without test case coverage, you can add a condition that filters for work items that do not have a related test case:
Then you would just need to add a Work Items widget from the Change and Configuration Management catalog to the dashboard:
And use the new query as the source for your dashboard widget:
Result:
Would that give you the information you need?
If you want to identify work items without test case coverage, you can add a condition that filters for work items that do not have a related test case:
Then you would just need to add a Work Items widget from the Change and Configuration Management catalog to the dashboard:
And use the new query as the source for your dashboard widget:
Result: