How to schedule and track test execution against the calendar in RQM?
Hello!
I still find impossible to create a real test schedule plan (manul activity not automatic) and then track the progresses of the test against it. What I need is to plan every test execution record for a spefic day or at least enqueue them in a backlog. Moreover when the TER are executed I would like the plan be able to show the progresses on TER (executed, failed, passed, etc).
Does someone know how to do this in RQM?
Thanks and best regards,
Matteo
3 answers
Feel free to add your requirement over there
Comments
Hello Bhuiya,
I'm not referring to Execution Schedule objects (that are related to automation testing). I'm referring to Test Schedule section of the test plan. I think that is clearly unsatisfactory in terms of planning and tracking of the test activities. Requirements in this area could be:
1. Ability to assign a planned execution date for each Test Execution Record [or better enque them into a backlog]
2. Ability to track the execution with automatic update of the plan from the Test Executed Records, in other words I need to know how many test have been completed, how many are remaining as of the date and if the test execution is ahead or late on the planned schedule.
Comments
I have tried also this functionality in 4.0.1 and still is far to be satisfactory for real usage. For example:
1. Even if related to iterations, the milestones data are not related to the plan content and not updated according to the execution:
1.1. The Points are not the sum of the points of the test cases
1.2 There is not Actual (Points and Dates) information.
2. The progress bars are cool and useful for a quick view but are not really usable reports. The need is to see and use the real data to be exported in excel for example. Or tatus reports and graphs to be inluced in status meeting presentation, etc etc.
3. Items in the Iterations are not usabe like in RTC... I cannot create an iteration Plan to see and manage my Test Execution Records