Advanced Burndown Report
Hi,
I'm trying to use the Advanced Burndown Chart available in RTC but the graph results in empty bars.
I configured my project area as needed (I think) having a release plan with child iterations, but when executing the report the created chart show empty bars (which should represent the story point of the required work).
Can anyone help ?
I configured my project area as needed (I think) having a release plan with child iterations, but when executing the report the created chart show empty bars (which should represent the story point of the required work).
Can anyone help ?
Thanks.
One answer
Hi Tal,
Underneath the report, I see the following info:
* INFO: This burndown report will create predictions based on release backlog size in complexity points and previous velocity. To create the full chart, ensure that you have specified an end date for the release and that you have created and selected iterations up to the release end date. Note that if you create new iterations, you must also update the data warehouse snapshots for this report to recognize those new iterations.
Have you specified an end date for the release and created and selected iterations up to the release end date? If the data collection jobs have not been run recently, you can kick them off manually by authenticating as an admin user, clicking the gear icon in the upper right-hand corner, choosing Manage Reports, and then Run all data warehouse collection jobs.
Underneath the report, I see the following info:
* INFO: This burndown report will create predictions based on release backlog size in complexity points and previous velocity. To create the full chart, ensure that you have specified an end date for the release and that you have created and selected iterations up to the release end date. Note that if you create new iterations, you must also update the data warehouse snapshots for this report to recognize those new iterations.
Have you specified an end date for the release and created and selected iterations up to the release end date? If the data collection jobs have not been run recently, you can kick them off manually by authenticating as an admin user, clicking the gear icon in the upper right-hand corner, choosing Manage Reports, and then Run all data warehouse collection jobs.