Our Sprint Backlog plan screen, beside the "Burndown" label, a message says: "Report not found."

I tried to fix it but I don't know what it needs. How do I fix that error message?

0 votes



3 answers

Permanent link
The report resources that is being looked for here is with the Report UUID : planning.Burndown. 

By deploying Planning Burndown to the specific Project Area the plan belongs to, the message you are noticing will be resolved.

To Deploy : Open Project in Eclipse Client > Team Artifacts View > Expand Reports Node > Right Click on Report Resources > Deploy New Resources :

Then Select the Planning Burndown :

hope it helps.

2 votes


Permanent link
Client: Web
Version: 3.0.1.1
Plan: Sprint 2 Backlog

Our Sprint Backlog plan screen, beside the "Burndown" label, a message says: "Report not found."

I tried to fix it but I don't know what it needs. How do I fix that error message?

If the problem is that you 'miss' some Reports (e.g. Burndown) in the 'Team Artifacts' view - Reports menu, you might have to Install missing reports in Rational Team Concert 3.0.

1 vote


Permanent link
Hi Dinesh,
               I faced the same problem that Naveen. I followed the steps explained by you and the issue was resolved.
Thanks for your help

Regards,

Liliana Mercado

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Jan 17 '12, 1:43 p.m.

Question was seen: 4,606 times

Last updated: Nov 19 '13, 8:09 a.m.

Confirmation Cancel Confirm