Jirong Hu (1.5k9295258) | asked Jan 09 '12, 1:55 p.m.
To unlock a resource, select it and right-click; in the menu, click Team > Unlock. A resource can be unlocked by the user who locked the resource or by a member of the JazzAdmins repository group.

The project team wants to have a couple of super users who will be able to unlock files when the file owner is on vacation. But from the above, only users belong to JazzAdmins can do that. Normally we only put RTC administrators in JazzAdmins group.

What you suggest if we want to give resource unlock permission to the project team?

Thanks
Jirong

One answer



permanent link
Geoffrey Clemm (30.1k33035) | answered Jan 09 '12, 9:32 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
In the current RTC 4.0 milestone, permission to remove other user's locks is controlled by the Source_Control -> Save_Stream -> Modify -> Stream -> Locking permissions.

I'm not sure when those permissions were added, but you can check to see if they are available in your project area.

Cheers,
Geoff

To unlock a resource, select it and right-click; in the menu, click Team > Unlock. A resource can be unlocked by the user who locked the resource or by a member of the JazzAdmins repository group.

The project team wants to have a couple of super users who will be able to unlock files when the file owner is on vacation. But from the above, only users belong to JazzAdmins can do that. Normally we only put RTC administrators in JazzAdmins group.

What you suggest if we want to give resource unlock permission to the project team?

Thanks
Jirong

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.