Question on best practice for Planned For field in Defects
I had a question on best practices with the Planned For field in RTC and how others are using it for defects.
When a defect is opened in an iteration what do you set for the Planned For field? Do you set it to the current iteration? And what if the defect is not going to be fixed in the current iteration? Do you move it to the Defect Backlog until it's planned for a future iteration? Right now we open them initially with the current iteration as the Planned For value. If they're fixed in the current iteration they're closed with the Planned For = Current Iteration. If not fixed, they're supposed to be moved to the Backlog but I'm finding they aren't always getting moved and instead stay in that previous iteration even after it's complete. |
2 answers
Geoffrey Clemm (30.1k●3●30●35)
| answered Dec 05 '11, 9:08 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
I'd suggest the following:
An open work item should never be planned for a completed iteration. In general, you want the Planned For field to be as accurate as you can make it. If you are not planning to fix it in the current iteration, it should not be Planned for the current iteration. You could instead plan it for the release (if you believe it will be fixed in the release), and then plan it for a specific iteration once you believe you know what iteration it will be fixed in. You should know well before the end of an iteration whether a given work item will be completed in that iteration (if not, that is a sign that the planning process needs to be improved). Cheers, Geoff On 12/5/2011 6:23 PM, miwalker wrote: I had a question on best practices with the Planned For field in RTC |
Thanks Geoff.
I'd suggest the following: I had a question on best practices with the Planned For field in RTC |
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.