How to define schedule days (Friday and Saturday) as off days in RTC?


SYED HUSSAIN (3719) | asked Aug 19 '14, 4:42 p.m.
Hello,

I have selected Sun to Thurs as schedule days in Timeline and created Release plan against it. In viw it still shows Sunday and Saturday as off days.

Any limitations? Or I am missing anything.

Also I am not able to import xml from MS project 2010 into RTC. (It starts project with 2-3 days delay).

Accepted answer


permanent link
Eric Jodet (6.3k5111120) | answered Aug 20 '14, 2:47 a.m.
JAZZ DEVELOPER
 Hello,
I think you need to set-up the work environment:

Hope it helps,
Eric
SYED HUSSAIN selected this answer as the correct answer

Comments
SYED HUSSAIN commented Aug 20 '14, 5:40 a.m.

Thanks a lot Eric. I got the same solution.


Eric Jodet commented Aug 20 '14, 5:45 a.m.
JAZZ DEVELOPER

 Excellent.

Glad to help here.