It's all about the answers!

Ask a question

How does Agile scheduler work for SCRUM projects


Vidhya Prakash (852933) | asked Oct 20 '11, 10:02 a.m.
What are the factors that determine the automatic calculation of project schedule in a Scrum project? How are the scheduled start & end dates calculated?

One answer



permanent link
Sharoon Shetty Kuriyala (55133) | answered Oct 20 '11, 10:16 a.m.
JAZZ DEVELOPER
Hi,

Scheduling happens like this:

* Get all work item assigned to a person in an iteration
* Sort them by their sequence value (this is *not* the rank)
* If the sequence value isn't set or equal use the rank
* Sum up the effective estimates of all n work items to figure out the start date of work item n+1

For a formal project it also takes scheduling constraints and dependencies into account.

The magic sequence value is set by using the drag and drop reordering in the MyWork view. See https://jazz.net/library/article/593#myWork for reference

Note: I am not sure what is referred to as scheduled start & end dates here.

Thanks,
Sharoon - Planning Team

What are the factors that determine the automatic calculation of project schedule in a Scrum project? How are the scheduled start & end dates calculated?

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.