It's all about the answers!

Ask a question

Using WorkItem from ScrumProcess in FormalProcess?


Raphael Weisser (10195) | asked Nov 05 '10, 4:59 a.m.
Hi,

every Process has it's own workitems.
I would like to have the story, epic from ScrumProcess and some others from Formal Process, which I also have choosen in ProcessConfiguration.

How can I use (export/import) workitemtypes from another process?

One answer



permanent link
Jared Burns (4.5k29) | answered Nov 05 '10, 2:58 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Hi,

every Process has it's own workitems.
I would like to have the story, epic from ScrumProcess and some others from Formal Process, which I also have choosen in ProcessConfiguration.

How can I use (export/import) workitemtypes from another process?


I don't believe there's any simple way to do this.

You'd manually copy over all of the workitem configuration pieces that you want from a Scrum project into your Formal Process project (or vice versa).

- Jared

Your answer


Register or to post your answer.