It's all about the answers!

Ask a question

DW / Data Collection Jobs for specific Projects in CLM 6.0.2


Salman Shaikh (23413875) | asked Apr 02 '17, 4:55 p.m.

Can we start data collection jobs for only specific projects so that it will consume less time than running all Data Collection Jobs for all Projects?. Can we limit it through any way ?

One answer



permanent link
Kevin Ramer (4.5k9186201) | answered Apr 07 '17, 11:01 a.m.

I don't think per project collection is possible.   I help manage what I think is a large deployment of RTC, QM, DNG with DCC's for each JTS.   Collections for most are once / day, but there are a few that run on intervals.   The majority of DCC jobs are in the seconds to minutes range.  Only the Work Items jobs run longer than 1h.


Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.