I need to sum all of the estimated hours for a set of work items. I have a query that identifies all of the items but I could not find a way to sum the estimated hours (short of paper & pencil).

RTC 2.0 Client
Rational Team Server 1.0.0.2

Thanks,
JEC

0 votes


Accepted answer

Permanent link
Hi,

if you can't use the plan's capabilities using Parent Child hierarchies I'd suggest to export your query to CSV files and use a spreadsheet to do the math. This would be at least a quick solution. Maybe there are other solutions as well.

Ralph

I need to sum all of the estimated hours for a set of work items. I have a query that identifies all of the items but I could not find a way to sum the estimated hours (short of paper & pencil).

RTC 2.0 Client
Rational Team Server 1.0.0.2

Thanks,
JEC
Jeff Care selected this answer as the correct answer

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Apr 08 '10, 2:38 p.m.

Question was seen: 8,544 times

Last updated: Apr 08 '10, 2:38 p.m.

Confirmation Cancel Confirm