I have two distinct Jazz systems, the first system serves a local team , while the second system was built to consolidate multiple teams. Assuming that the second system already host some projects (can't used backup/restore), how do I move the projects on the first system to second one. Also, the users might need to be mapped to the new ids of the second system.

0 votes



One answer

Permanent link
In RTC 1.0, you cannot migrate data at the project level. You can only
migrate the entire repository to another DB. Also because the user
limit is set at 250 licensed users, you typically would want to have
unique servers hosting large projects so that you don't run out of licenses.

Matt Lavin
Jazz Server Team


abaror wrote:
I have two distinct Jazz systems, the first system serves a local
team , while the second system was built to consolidate multiple
teams. Assuming that the second system already host some projects
(can't used backup/restore), how do I move the projects on the first
system to second one. Also, the users might need to be mapped to the
new ids of the second system.

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Sep 04 '08, 6:46 a.m.

Question was seen: 3,644 times

Last updated: Sep 04 '08, 6:46 a.m.

Confirmation Cancel Confirm