I have a plan (phase plan, cross project plan or release plan) with several plan items inside in project area "A". Some of the plan items have children and/or contributors in project area B. In the plan from project area A, I want to see only the contributors or children of project area "B".
I've already tried in the plan to EXCLUDE->EXPRESSION->!projectArea:B. But this causes that all items are gone.
Can someone help me to see just the items of the project area "B" including their parent?
My EWM version is 7.0.1
|
One answer
Ralph Schoon (63.6k●3●36●46)
| answered Sep 27 '20, 9:09 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER edited Sep 27 '20, 9:14 a.m.
I don't know an answer to the original question at the moment, but I have to point out that the planning component does not support any planning capabilities for parent/child relationships across project area boundaries.
Only tracks/contributes to in cross project plans have an meaning across project area borders.Parent/child relationships for planning only work within a project area.
I know this is documented, I just don't have a document link at the moment.
Given that, there might be no expression support for this.
|