No impact of start no earlier than restriction of plan items

Hello!

I have a planning item with several tasks / execution items as children. I restricted the parent item to "start no earlier than" in one of my plans and expected that this would have an effect on the planning item itself and its children. It does not however.

Is this the expected behaviour, and how could I reach what I expect?
Actually the the structure of items is more complex: More levels of nesting and more items. Do I need to change the restriction for each and every item?
This would be really inconvenient...

Thanks in advance!

0 votes



One answer

Permanent link
I am sure this restriction works if the workitem relationship is "depends on". I'm not sure about parent-child relationship. Maybe you could use "depends-on" instead?

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,020
× 239

Question asked: Apr 12 '16, 8:28 a.m.

Question was seen: 3,323 times

Last updated: Apr 12 '16, 11:24 a.m.

Confirmation Cancel Confirm