JRS - Sprint burndown graph for specific members only

Greetings to all!


We need a JRS report that will graph the Sprint burndown for specific members, not an entire team. We are not able to identify, which conditions and artifacts to use, or, if there is a template, that we can tweak to achieve such a report.

Any help would be very kind and helpful!

0 votes

Comments
In a burndown I think you are trying to track the total work remaining. You might want to use a custom trend report to create a custom burn down.

Have a look at these articles:

Start with the Historical Trends type. The Time Range is during your Sprint. Then you can add as condition the Planned For and specify the Sprint Iteration. You can also specify the Owner of the work item here (assuming they have been made the Owner).


Be the first one to answer this question!

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 1,220
× 360
× 23

Question asked: Oct 21 '19, 1:53 p.m.

Question was seen: 1,132 times

Last updated: Oct 23 '19, 3:16 a.m.

Confirmation Cancel Confirm