It's all about the answers!

Ask a question

Can I change the color of the accumulated time bars?


Akhir Alibhai (1115) | asked Aug 24 '17, 10:10 a.m.

 When looking at the tree view for a plan, is it possible to have different colors for the accumulated time bars. Would it be possible to have a different color for each work item type, or for a specific branch on the plan?

One answer



permanent link
Ian Wark (79713553) | answered Aug 25 '17, 12:45 a.m.

I don't think this feature exists. The progress bars and load bars show pre-programmed colors to express different information. See here: https://jazz.net/library/article/586

If you wish to raise an enhancement you can here. But you should take time to understand how the time bars work and be specific mentioning which exact plan type and bar type etc..

RFE Community
https://www.ibm.com/developerworks/rfe

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.