How to Planned Start Date and Planned End Date Attributes editable in 06-p Server


vamshi s (11) | asked Feb 02, 5:27 a.m.

 Hello Team,

For a task workitem  in ALM  06-p server , Currently we see "Planned Start Date and Planned End Date " Attribute values are set to "None" and non-editable. Can someone please guide how to make these attributes editable with "Timestamp".


Thanks in advance

One answer



permanent link
Ralph Schoon (63.5k33646) | answered Feb 02, 5:37 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER

 No, you can not edit these, and there is no way to make them editable. These are pseudo attributes that are calculated by the planning component. In order to have them show anything it is necessary to have an owner assigned to the work item. The owner must have work allocation for the team/project area that the work item is filed against.


Comments
Ralph Schoon commented Feb 02, 6:32 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER

In addition, I suspect that the process is based on the Traditional/Formal planning template. Dependencies between items can be defined using the successor/predecessor links.