How to Planned Start Date and Planned End Date Attributes editable in 06-p Server

 Hello Team,

For a task workitem  in ALM  06-p server , Currently we see "Planned Start Date and Planned End Date " Attribute values are set to "None" and non-editable. Can someone please guide how to make these attributes editable with "Timestamp".


Thanks in advance

0 votes



One answer

Permanent link

 No, you can not edit these, and there is no way to make them editable. These are pseudo attributes that are calculated by the planning component. In order to have them show anything it is necessary to have an owner assigned to the work item. The owner must have work allocation for the team/project area that the work item is filed against.

0 votes

Comments

In addition, I suspect that the process is based on the Traditional/Formal planning template. Dependencies between items can be defined using the successor/predecessor links.

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,023

Question asked: Feb 02 '24, 5:27 a.m.

Question was seen: 547 times

Last updated: Feb 02 '24, 6:32 a.m.

Confirmation Cancel Confirm