How to get a week on week status changes in RTC using JRS?


Dhanya Saseendran (8831621) | asked Jan 24 '16, 11:30 p.m.
Hi,
We have queries in our Project Area which shows the number of work items in the status 'deployed', 'under development', 'documentation' etc. The query shows the number of workitems in these status in a table format at any point in time.


We want to understand what was the numbers for the last week. So that we can understand how we are improving.. the week on week progress.

Please let me know if any further information needs to be given.
Thanks
Dhanya

Accepted answer


permanent link
Francesco Chiossi (5.7k11119) | answered Jan 25 '16, 2:55 a.m.
edited Jan 25 '16, 2:57 a.m.
Hello Dhanya,

I think your request can be accomplished using the historical metrics from the data warehouse.
They have been made available for reporting in JRS in the latest version 6.0.1.

For more details see the "Workflow for reports on historical metrics" section of

Jazz Reporting Service 6.0.1 New & Noteworthy
https://jazz.net/downloads/jazz-reporting-service/releases/6.0.1?p=news

Best Regards,

Francesco Chiossi
Dhanya Saseendran selected this answer as the correct answer