Changing Iteration Dates doesn't seem to propogate to Report
RTC 3.0.1.6 (will be upgrading to 6.0.1) Using the Scrum template. I have the default sprint 1 and sprint 2 iterations and I update the generated dates to actual dates of the project. I go to the Sprint Burndown report from the dashboard and the details show the iteration date the report is using is the old generated dates which are incorrect.
i.e. the date range of Sprint 1 was April 13 - May 3rd, and I changed those to May 18th - May 31, saved this. I then go to the dashboard for the project, go to the Sprint Burndown and the About this Report shows the iteration date range is the old date range. It's been about an hour and the same old date range still appears. I'm wondering if the date range change hasn't propagated yet or if there is something wrong, or something I'm not doing correctly.
|
Accepted answer
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.