![]() In 4.0.2, is there a way to add up all estimation duration from child tasks and to have the result in the parent task? Thanks. |
One answer
![]()
Ralph Schoon (62.0k●3●36●43)
| answered Sep 07 '15, 5:49 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
This would require an extension like
RTC Update Parent Duration Estimation and Effort Participant |