Move work items from product backlog to sprints? (several items at the same time)
![]()
How can I move the work items from the product backlog to the sprints? Is there a possibility of adding several work items at the same time to the sprints or do I have to assign every single task to the sprints?
|
One answer
![]()
From a plan view, you can select multiple work items and then plan all selected items for an interation. Example:
Comments There was the another issue mentioned here. I have moved the question to https://jazz.net/forum/questions/221863/save-conflict-when-saving-multiple-work-items
|