It's all about the answers!

Ask a question

Using CQ, DCC and Insight together


David Mehaffy (90123338) | asked May 28 '15, 12:24 p.m.
JAZZ DEVELOPER
 We have a custom ETL to collect data from CQ into our DataWarehouse.  We would like to migrate to using DCC for the data collection for the CLM portions of our data (CQ is defect provider to QM).  Is there a way in dcc wrapper to specify collecting only the ODS data.  We want to split the ODS collection from Metrics and only run the Metrics once a day.

One answer



permanent link
Rafik Jaouani (5.0k16) | answered May 28 '15, 3:22 p.m.
JAZZ DEVELOPER
Hi David, from DCC you can disable all the metric jobs. That way only the ODS jobs would run. Are you also looking into running the metric jobs using Data Manager?

Comments
David Mehaffy commented May 28 '15, 4:42 p.m.
JAZZ DEVELOPER

 If I disable the metrics then how will I run them at a later time from the wrapper.  I want to say schedule to run the ODS jobs every 30 minutes and the metrics once a day.  I need to do this from Insight because I need to have the CQ ETL run before the ODS data each time.

Your answer


Register or to post your answer.