Descriptive Change Sets - Precondition
2 answers
Hello,
I guess you need "Require Work Item" operation behavior.
Eric
Comments
Added "Require Work Item" as well, when user with Jazz Admins, Jazzdwadmin, tries to deliver the code, it will ask to associate change set and work item, when other user with Jazz user and Jazz Guest, with out associating comments/work items, allows to deliver the code.
Problem is fixed. We use master and slave project area, user is not added to master project area.
Hi Dhruva
The user's should always be added to the Child PA's and should not be a part of the Master PA's except the Administrators.
Managing Rational Team Concert work item changes with process sharing:
https://jazz.net/library/article/1077
The problem may be fixed for you, but you might need to review the permissions and preconditions in your process template project level, team level and iteration level.
The user's should always be added to the Child PA's and should not be a part of the Master PA's except the Administrators.
Managing Rational Team Concert work item changes with process sharing:
https://jazz.net/library/article/1077
The problem may be fixed for you, but you might need to review the permissions and preconditions in your process template project level, team level and iteration level.