Create new Task Template filed Agianst lost

Hi, i´m using RTC 4.0.6 i have create an structure of parent plan items and task and asigned one filed against to some tasks and another filed against to another tasks ... then i create a new Task template from that structure in Eclipse client
but when i deploy the Template to the plan filed against configuration is missing and all task are assigned to the same filed against.
what i´m missing?
Thanks a lot
but when i deploy the Template to the plan filed against configuration is missing and all task are assigned to the same filed against.
what i´m missing?
Thanks a lot
2 answers

Hello Eric,
check your process template follow-up actions.
Take SCRUM Template as example: you'll notice a create category action,
where you can specify your categories - which values will populate the Filed Against combo.
Open Template, and go to Process Configuration tab.
Go to Project Initialization, and add the follow-up action to create your categories.
Hope it helps,
Eric
Comments

Thanks Eric, but my issue is that i need to create a task template and the filed against for some tasks in the template must be for example group A .... and for another group of tasks in the Task Template must be Group B in the filed against combo ....

Hello,
right - now I understand you were talking about work item templates,
and no Process Templates.

Tested with RTC 4.0.5
- created 2 categories - cat1 and cat2
- created 2 tasks filed against cat1
- created 2 tasks filed against cat2
- created a new work item template
- added the 4 tasks (did not check the attribute variables)
- created new work items from this template
observed:
- 2 tasks created with filed against cat1
- 2 tasks created filed against cat2
Not sure if this is what you're trying to do.
Eric
Comments

yes that´s is what i´m trying to do but when i deploy my task template all the tasks are created with filed against (in your case ) with cat1, the ones i selected to Cat2 are changed to Cat1 in the deploy of the task template

Eric,
what is the template you're using? Formal Project Management?