Hi, i´m using RTC 4.0.6 i have create an structure of parent plan items and task and asigned one filed against to some tasks and another filed against to another tasks ... then i create a new Task template from that structure in Eclipse client
but when i deploy the Template to the plan filed against configuration is missing and all task are assigned to the same filed against. what i´m missing? Thanks a lot |
2 answers
Tested with RTC 4.0.5
- created 2 categories - cat1 and cat2
- created 2 tasks filed against cat1
- created 2 tasks filed against cat2
- created a new work item template
- added the 4 tasks (did not check the attribute variables)
- created new work items from this template
observed:
- 2 tasks created with filed against cat1
- 2 tasks created filed against cat2
Not sure if this is what you're trying to do.
Eric
Comments
Eric Tagtachian
commented Jun 26 '14, 7:27 a.m.
yes that´s is what i´m trying to do but when i deploy my task template all the tasks are created with filed against (in your case ) with cat1, the ones i selected to Cat2 are changed to Cat1 in the deploy of the task template Eric,
what is the template you're using? Formal Project Management?
|