Jazz Forum Welcome to the Jazz Community Forum Connect and collaborate with IBM Engineering experts and users

Actual time reporting from RTC? Time Spent incorrect and all appears manual, nothing in delivered reporting options

 I am desperately looking for ways either within RTC or exporting from RTC into Excel or other tools, that I can truly extract the # of hours "Actual Hours" spent on a given task/work item, etc. Unfortunately, using the Jazz reporting, we cannot report on actual time and the time spent, is usually blank in tasks/work items where many hours are applied. 

Please help! I need to report on this but not sure the best way to do so. 

0 votes

Comments

Hi Rebecca

I think I understand what you are trying to do but unclear why there is no time entered on the tasks/work items.  Did people not enter their actual time, or is this an error you are seeing? 

What version of RTC are you using, and what project area process template are you using (eg: 4.0.5 and the Scrum template)?

anthony


Be the first one to answer this question!

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 1,220

Question asked: Jun 16 '14, 5:14 p.m.

Question was seen: 4,353 times

Last updated: Jul 01 '14, 5:41 p.m.

Confirmation Cancel Confirm