I'd like to be able to reorder the presentation of Work Item types in the main menu. Is this possible?
When creating new work item types in the Eclipse Client they default to last in the menu. Using 4.0.3. |
One answer
Partial answer:
I was able to reorder the Work Items menu by changing the order in the Process Configuration Source XML. It's in the data section under project-configuration. project-configuration data com.ibm.team.workitem.configuration.workItemTypes Reordering the <type> tags reorders the menu. Haven't found a built in way of reordering. Comments
sam detweiler
commented Feb 21 '14, 1:40 p.m.
you did it the only way available today..
Tim Fuller
commented Feb 21 '14, 1:45 p.m.
Thanks for the confirmation.
|