From my understanding, in order to associate a Test plan to a secondary timeline, you need to enable timelines and team areas. The dilemma is that although we have multiple releases on the fly at any given time: both main development and maintenance. There is only one test team working on validating these releases. But it seems that RQM requires that multiple team areas be created, one per timeline, in order for a test plan to be associated with one of those secondary timelines. This results in us having to create fake teams in order to perform this association.

Is this a hard requirement? Or is there a way to associate a test plan with a secondary timeline with the need to create all these team areas?

0 votes



One answer

Permanent link
Hi, having multiple team areas doesn't really mean different teams, for example, you can have the developent and maintenance team areas and both of them can have the exact same team for both without problems. Answering your question, yes, you need to create a team area for each timeline you need. 

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,014
× 6,117

Question asked: Nov 04 '13, 10:05 a.m.

Question was seen: 4,800 times

Last updated: Nov 26 '13, 10:51 a.m.

Confirmation Cancel Confirm