multiple iterations in a release plan
how do I get multiple iterations to be included in a release plan in RTC 4.0.3 for a traditional project life cycle.
i have 4 iterations for reqs, design, implementation, test..............I'd like to have all of these be part of the top level release plan |
One answer
Ross,
While managing your project, you can define the hierarchy of iterations as needed. Then in your release plan, select the top-level iteration that represents a release and it will display its child iterations in the hierarchy. Also, make sure the plan view for your release plan has these options: Group: Iteration, Display: Tree: Parent-> Children, as the default "Work Breakdown and Schedule" is defined. |