folks,

I'd like to have others review and approve a phase plan in team concert. This functionality seems not to be included in 4.0.3 using the traditional project management process. is this functionality included and I just can't find it or it is an enhancement. What is the rationale for not including this functionality?

Accepted answer


permanent link
Stephanie Bagot (2.1k512) | answered Nov 11 '13, 2:50 p.m.
FORUM MODERATOR / JAZZ DEVELOPER
Do you mean the ability to approve plan creation? This feature isn't in RTC 4.0.4. I wasn't able to find an enhancement request either, so it is possible this feature/functionality is not included in RTC since it was never requested.

I encourage you to create an Enhancement request for this feature.
ross jones selected this answer as the correct answer

Comments
ross jones commented Nov 11 '13, 5:29 p.m.

i will submit an enhancement request

One other answer



permanent link
Geoffrey Clemm (29.9k23035) | answered Nov 23 '13, 2:34 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
I'd just create a "review plan" work item, and then add approvals to that work item.