Jazz Forum Welcome to the Jazz Community Forum Connect and collaborate with IBM Engineering experts and users

How I can view resource allocation across project ?

If I have a resource allocated on more projects. I don't undestand  how to view the total resource allocation (across projects).

I'm using  RTC 4.0.1.

0 votes


Accepted answer

Permanent link
Use BIRT, there is no Widget

you need to connect APT_SNAPSHOT and COMMON_SNAPSHOT

I can send you my xml file if you'd like.  erwin.kunz@siemens.com
lorenzo tiberi selected this answer as the correct answer

0 votes


2 other answers

Permanent link
 Hi Lorenzo,
                     This is possible using Birt or Insight reporting. Not sure if any direct widget is available in RTC 4.0 for this - You can check the available widgets.

Thanks.

0 votes


Permanent link
Thanks Erwin,
we have Publishing Engine for generating report and documents.
I hope that the xml file is suitable in RPE.

tiberilo@posteitaliane.it

regards


0 votes

Comments

Does the file also work in RPE, Iorenzo?

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 1,221

Question asked: Mar 12 '13, 6:35 a.m.

Question was seen: 5,185 times

Last updated: Apr 30 '13, 8:47 a.m.

Confirmation Cancel Confirm