Why RTC Plan work progress load showing +0.75h?

My Sprint is 1 day, 9:00 AM to 6 PM in same day (b'cas its easy sample)

  


Work Day is 8 hour....

My work env - work day 8 hour  
I create a release plan with ss1 sprint. And create a work item 1 day estimation. Load Progress is 8/8.75

What is this 0.75h? And Why it is showing in here? Is it launch break :) If it is, how can i set it another value?

Work item estimate 8 hour but plan 8.75

0 votes



2 answers

Permanent link

 Please see https://jazz.net/library/article/586 for how those bars work.


No way to tell where the 8.75 comes from here. Note that is calculated for the whole team and not only for one person. 

0 votes


Permanent link

See also Assessing team work with progress and load bars.


Ken 

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 1,381
× 1,220

Question asked: Oct 12 '18, 11:01 a.m.

Question was seen: 2,543 times

Last updated: Oct 25 '18, 3:24 p.m.

Confirmation Cancel Confirm