Why RTC Plan work progress load showing +0.75h?
My Sprint is 1 day, 9:00 AM to 6 PM in same day (b'cas its easy sample)
Work Day is 8 hour....
I create a release plan with ss1 sprint. And create a work item 1 day estimation. Load Progress is 8/8.75
What is this 0.75h? And Why it is showing in here? Is it launch break :) If it is, how can i set it another value?
2 answers
Please see https://jazz.net/library/article/586 for how those bars work.
No way to tell where the 8.75 comes from here. Note that is calculated for the whole team and not only for one person.