Unable to add resource from Plan in 4.0.1
Open a formal plan that is associated with a team area and not a project area.
Go to Resources tab
Add Resources
Select a user and check for availability
Add the resource alloation to the plan and close the dialog
Save the plan.
>> Throws the following exception
Process area name must not be empty.
com.ibm.team.process.internal.service.ProcessService.validateProcessAreaPreSave(ProcessService.java:3015)
Go to Resources tab
Add Resources
Select a user and check for availability
Add the resource alloation to the plan and close the dialog
Save the plan.
>> Throws the following exception
Process area name must not be empty.
com.ibm.team.process.internal.service.ProcessService.validateProcessAreaPreSave(ProcessService.java:3015)