Moving a work item to another iteration plan hangs


Aradhya K (1.4k54345) | asked Jan 24 '13, 11:00 a.m.
JAZZ DEVELOPER
1. Login to RTC Admin UI
2. Create a Project from the formal template
3. Go to ccm/web/project created and create a Workitem planned to Release 1.0 
4. Open all Current plans
5. Open Release Plan
6. Create a new view as per below
7. In Column Display Select > Due Date , Estimate , Accumulated Time and Accumulated time Ready Only.
8. In options > Add Group by iteration and Display > Tree > Included in Promotion and --> Promoted Work Item.
9. Add a few WI in different iteration.
10. Now try to move the WI from one iteration to another.

While moving the WI from one iteration to another using the plan view. The error is thrown in firebug console and the move process does not complete. There is no hang actually. You can refresh the page and reload the page or navigate on the current page, 

One answer



permanent link
Aradhya K (1.4k54345) | answered Jan 24 '13, 11:01 a.m.
JAZZ DEVELOPER
The problem is recognized as a defect.