I'm trying to add a task to my QM-testplan.
Which workitem-editor is being used? The problem is the current editor is not showing fields which are required (for instance 'Planned For') for the workitem. |
One answer
It must be using RQM's default workitem editor. Configure it using RQM's project area administration page.
|
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.
Comments
The fields I see are:
However, when saving the task (quality task), I get this error:
'Save Work Item' failed. Preconditions have not been met: The 'Planned For' attribute needs to be set (work item <02:49:07>). The 'Planned For' attribute needs to be set (work item <02:49:07>)