We use RTC (v.3.0.1) to track our test work and we have our test cases in RQM (v.3.0.1). We can link the test case to a RTC task but it seems to be not possible to link the TER. The TER is the current execution of the test case, contains the information from the execution and defects. It is in our eyes much better to link this as to link the test case. Can someone help to get this linked?

1 vote



One answer

Permanent link
The only way that I can see to do this is to add a "related artifact" type link in RTC and provide the URL of the TER.

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,019

Question asked: Aug 20 '12, 8:48 a.m.

Question was seen: 4,458 times

Last updated: Aug 20 '12, 11:21 a.m.

Confirmation Cancel Confirm