How do a synchronize a sandbox that is out-of-sync after cancelling an Accept action?
Hi,
When Accepting change-sets in the 'pending changes' view, there is possibility to cancel the Accept action.
Choosing this option (cancel) will make the project 'out of sync'.
Is it possible to disable the 'Cancel' option or create a restore operation that will rollback the project to it's last state before the Accept action?
Our Eclipse project is very huge and re-sync it takes lot of time..
What can we do?
Thanks.
When Accepting change-sets in the 'pending changes' view, there is possibility to cancel the Accept action.
Choosing this option (cancel) will make the project 'out of sync'.
Is it possible to disable the 'Cancel' option or create a restore operation that will rollback the project to it's last state before the Accept action?
Our Eclipse project is very huge and re-sync it takes lot of time..
What can we do?
Thanks.
One answer
Disabling the cancel option is not possible. Re-syncing the project would be similar to the restore operation you suggest. It checks the files and only downloads the ones that are out-of-sync. If you have another suggestion for a restore operation, you will have to open an enhancement against RTC Source Control. Perhaps "Out of sync" inconsistency, enhance error handling, avoid out of sync situations (165630) is what you would like to see.
Comments
Geoffrey Clemm
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER Jul 04 '12, 11:20 a.m.Please remember to phrase your question in the form of a question.