Why doesn't Planned for show the timeline based on Team Area?

 Using RTC 4.0.6

Created a Project with Team areas based on Functional team and associated each to respective Categories.
Team are actively using the project area.
Added Timeline such that each Team area can have individual timeline association.

When updating a Task to select timeline (Planned For) the timeline iterations do not show up based on the selected Team area and shows a different Timeline. (I did verify that the category associations were correct).

The same behaviour happens when I create  a new work item.

Is this a defect? or is there a step not being done correctly?

0 votes


Accepted answer

Permanent link
sounds like a bug. planned for attribute is marked as dependent on project area and category.
Radha Sastrigal selected this answer as the correct answer

0 votes


One other answer

Permanent link
Enhancement Work item filed against category should filter 'planned for' elements (81316) requests the behavior you are looking for.   Please feel free to vote for this item, and/or add a comment, to indicate your support.

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Dec 19 '14, 12:54 p.m.

Question was seen: 3,121 times

Last updated: Dec 19 '14, 4:01 p.m.

Confirmation Cancel Confirm