Formal Project Management Template and CLM 2012


Steve Briand (411717) | asked Jun 26 '12, 4:54 p.m.
Have there been any changes or improvements to the Formal Project Management Process template in CLM 2012?  I know Plan Item 169814 was Planned For 4.0, but I don't see anything indicating it was implemented.

One answer



permanent link
Aradhya K (1.4k44345) | answered Jun 27 '12, 1:46 a.m.
JAZZ DEVELOPER
As far as I know 
1. There is one change in the Gantt chart. We will be able to select which schedule to be shown. Any or all of Current, Proposed or Planned can be selected.
2. The MSP import feature has got a face lift and now we can update the estimates on re-import.