Formal Project Management Template and CLM 2012

Have there been any changes or improvements to the Formal Project Management Process template in CLM 2012?  I know Plan Item 169814 was Planned For 4.0, but I don't see anything indicating it was implemented.

1 vote



One answer

Permanent link
As far as I know 
1. There is one change in the Gantt chart. We will be able to select which schedule to be shown. Any or all of Current, Proposed or Planned can be selected.
2. The MSP import feature has got a face lift and now we can update the estimates on re-import.

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Jun 26 '12, 4:54 p.m.

Question was seen: 3,709 times

Last updated: Jun 27 '12, 1:46 a.m.

Confirmation Cancel Confirm