If an user is in more than one team, s/he can be over-assigned. This can happen in the following situation:
Two work items are assigned to the same user and targeted on the same iteration, but in different categories, which belong to different teams. In the time-boxing view for the different plans for the two categories there is only one work item visible in either case. So, the user can be assigned to two work items in the same time frame. Possible solution: Show all work items of the group's users even if some of these work items belong to a different team. Such work items should be grayed-out and read-only. |
2 answers
Hi Markus,
we thought about solving the problem as you described in https://jazz.net/forums/viewtopic.php?t=167. If we need a more dynamic solution in the future, we will implement it along the lines you outlined here. Thanks, MikeS mschille wrote: If an user is in more than one team, s/he can be over-assigned. This |
Hallo Michael,
as mentioned in https://jazz.net/forums/viewtopic.php?p=650#650 we should follow up the proposals via https://jazz.net/forums/viewtopic.php?t=164. and wait for the new planning functionality. Kind regards, Markus Hi Markus, If an user is in more than one team, s/he can be over-assigned. This |
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.